B.C. Highway Flood Recovery Projects - Highway 11

Last updated on May 7, 2024

Repair work on Highway 11

Work continues on Highway 11. Find out about current road status.

Traffic update

Traffic pattern change as construction begins.

April 29 - May 12
9 am - 3 pm - Single lane closures
Preliminary work to shift lanes to accommodate repairs and paving.

June-October

The four lanes of Highway 11 will be shifted slightly between Valley Road and Bateman Road.


Allow for extra travel time.

Reduces speed limit will be in effect through the area.

Obey signage and traffic-control personnel.

Check DriveBC for conditions and events that may be affecting Highway 11.

Location

  • Highway 11 between Valley Road and Bateman Road

Status

  • Out for tender
  • Southbound repairs: Completed
  • Northbound repairs: In design
    • Final phase of the northbound repairs is currently out to tender
    • Preliminary Day Labour work is happening to allow the road to be shifted during construction

Photo gallery

Contact information

For more information contact:
Valerie Fabick
Project Manager